During the final phase of Ramtech’s construction of Blue Ridge ISD’s middle school, we began the demolition of some existing structures and the extensive site work required for a two-story 28,200 square foot elementary school building, expanded parking area, and new road. The ABS permanent modular construction approach was then used to manufacture and construct a facility that features 17 classrooms, two science labs, administrative office space, and a combined library and media center. Like the middle school, the building has integrated data, communication, and alarm systems, as well as a mechanical and lighting system designed to accommodate the District’s energy management system. The new school also incorporates a full-height split-faced block exterior to match the other surrounding structures.

Building & Construction Details: Permanent Modular Construction

Project Size: 28,200 sq ft

Construction: IBC Type

Contract Type: Direct purchase through purchasing co-op

Facility Use: Two-story elementary school with elevator

Description: 17 classrooms, 2 science labs & prep room, administrative office, computer lab, & library. Parapet wall profile with masonry exterior designed to match adjacent high school.

Completion: 10 months

TOP